Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Premium Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
Categories
- Not categorized 0%
Unlock Your Full Report
You missed {missed_count} questions. Enter your email to see exactly which ones you got wrong and read the detailed explanations.
Submit to instantly unlock detailed explanations for every question.
Success! Your results are now unlocked. You can see the correct answers and detailed explanations below.
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
You have recently joined a credit union as MLRO. Your first major assignment involves NEC – Article 110 (Requirements for Electrical Installations) during outsourcing, and a regulator information request indicates that the newly installed 480V AC PV combiner box in the facility’s mechanical room may not meet clearance standards. The box is mounted on one wall, directly facing a finished concrete block wall 40 inches away. During your internal audit of the system’s compliance with safety standards, you must determine if the current installation provides sufficient clearance. What is the minimum depth of the working space required for this equipment according to the NEC?
Correct
Correct: According to NEC Table 110.26(A)(1), for systems operating between 151 and 600 volts to ground (which includes a 480V system, typically 277V to ground), Condition 2 applies when there are exposed live parts on one side and grounded parts on the other. Concrete, brick, or tile walls are considered grounded. For this voltage range under Condition 2, the minimum clear working space depth is 3.5 feet.
Incorrect: 3.0 feet is the requirement for Condition 1, where there are no grounded parts on the opposite side of the working space. 4.0 feet is the requirement for Condition 3, where there are exposed live parts on both sides of the working space. 2.5 feet is not a standard minimum depth for equipment operating at this voltage level under any condition in Article 110.
Takeaway: Working space depth requirements are determined by the voltage to ground and whether the opposite surface is considered a grounded or live part as defined in NEC Table 110.26(A)(1).
Incorrect
Correct: According to NEC Table 110.26(A)(1), for systems operating between 151 and 600 volts to ground (which includes a 480V system, typically 277V to ground), Condition 2 applies when there are exposed live parts on one side and grounded parts on the other. Concrete, brick, or tile walls are considered grounded. For this voltage range under Condition 2, the minimum clear working space depth is 3.5 feet.
Incorrect: 3.0 feet is the requirement for Condition 1, where there are no grounded parts on the opposite side of the working space. 4.0 feet is the requirement for Condition 3, where there are exposed live parts on both sides of the working space. 2.5 feet is not a standard minimum depth for equipment operating at this voltage level under any condition in Article 110.
Takeaway: Working space depth requirements are determined by the voltage to ground and whether the opposite surface is considered a grounded or live part as defined in NEC Table 110.26(A)(1).
-
Question 2 of 10
2. Question
How should Ethical Considerations in PV System Inspection be correctly understood for NABCEP PV System Inspector (PVSI)? A PV system inspector is performing a final verification for a client on a newly commissioned 10 kW rooftop array. During the walkthrough, the inspector identifies that the DC disconnect is not readily accessible as required by NEC 690.13, despite the local building department having already issued a final green tag. The installation contractor suggests that since the AHJ has already approved the system, the inspector should align their report with the AHJ’s findings to maintain professional courtesy and avoid project delays. What is the most appropriate ethical action for the inspector?
Correct
Correct: According to the NABCEP Code of Ethics and professional standards for inspectors, the primary obligation is to provide an accurate, independent, and honest assessment of the system. Even if an Authority Having Jurisdiction (AHJ) has previously approved an installation, the inspector is hired to provide a professional verification. If a clear violation of the National Electrical Code (NEC) or safety standards is found, it must be documented. Professional integrity requires that the inspector does not succumb to pressure to overlook safety hazards for the sake of project timelines or professional courtesy.
Incorrect: Deferring to the AHJ’s decision when a violation is clearly present fails to meet the inspector’s duty of care to the client and the public. Omitting findings from a formal report based on a verbal agreement to fix them later is a breach of transparency and professional ethics. Treating an AHJ’s oversight as a valid field modification without actual compliance or official variance documentation is a misrepresentation of the system’s safety status and a violation of the inspector’s professional mandate.
Takeaway: A PV system inspector must maintain independent professional judgment and report all safety and code violations, regardless of prior approvals by other authorities or stakeholders.
Incorrect
Correct: According to the NABCEP Code of Ethics and professional standards for inspectors, the primary obligation is to provide an accurate, independent, and honest assessment of the system. Even if an Authority Having Jurisdiction (AHJ) has previously approved an installation, the inspector is hired to provide a professional verification. If a clear violation of the National Electrical Code (NEC) or safety standards is found, it must be documented. Professional integrity requires that the inspector does not succumb to pressure to overlook safety hazards for the sake of project timelines or professional courtesy.
Incorrect: Deferring to the AHJ’s decision when a violation is clearly present fails to meet the inspector’s duty of care to the client and the public. Omitting findings from a formal report based on a verbal agreement to fix them later is a breach of transparency and professional ethics. Treating an AHJ’s oversight as a valid field modification without actual compliance or official variance documentation is a misrepresentation of the system’s safety status and a violation of the inspector’s professional mandate.
Takeaway: A PV system inspector must maintain independent professional judgment and report all safety and code violations, regardless of prior approvals by other authorities or stakeholders.
-
Question 3 of 10
3. Question
Senior management at a payment services provider requests your input on NEC – Article 695 (Fire Pumps) as part of incident response. Their briefing note explains that during a recent facility-wide electrical audit following the installation of a 500 kW rooftop PV array, concerns were raised regarding the coordination between the PV system’s service interconnection and the existing fire pump’s power supply. As the PV System Inspector, you are reviewing the fire pump’s dedicated supply conductors and overcurrent protection to ensure they remain compliant with NEC requirements for reliability. In this context, what is the specific requirement for the overcurrent protective device(s) installed in the fire pump’s power circuit?
Correct
Correct: According to NEC 695.4(B)(2), the overcurrent protective device for a fire pump must be selected or set to carry indefinitely the sum of the locked-rotor current of the fire pump motor(s) and the pressure maintenance pump motor(s), plus the full-load current of the accessory equipment. This unique requirement ensures that the fire pump continues to operate under extreme conditions, prioritizing the suppression of fire over the protection of the motor itself.
Incorrect: Sizing at 125 percent of full-load current is a standard requirement for most motors under Article 430, but it is insufficient for fire pumps which must not trip under locked-rotor conditions. Coordinating the fire pump with the PV system as a primary source is incorrect because fire pumps require a highly reliable source, typically connected ahead of the service disconnecting means. Locating fire pump protection in a PV combiner box violates the requirement for fire pump sources to be independent and reliable, and it would introduce unnecessary risks of accidental shutdown.
Takeaway: Fire pump overcurrent protection is specifically designed to carry locked-rotor current indefinitely to ensure the pump operates until failure during an emergency.
Incorrect
Correct: According to NEC 695.4(B)(2), the overcurrent protective device for a fire pump must be selected or set to carry indefinitely the sum of the locked-rotor current of the fire pump motor(s) and the pressure maintenance pump motor(s), plus the full-load current of the accessory equipment. This unique requirement ensures that the fire pump continues to operate under extreme conditions, prioritizing the suppression of fire over the protection of the motor itself.
Incorrect: Sizing at 125 percent of full-load current is a standard requirement for most motors under Article 430, but it is insufficient for fire pumps which must not trip under locked-rotor conditions. Coordinating the fire pump with the PV system as a primary source is incorrect because fire pumps require a highly reliable source, typically connected ahead of the service disconnecting means. Locating fire pump protection in a PV combiner box violates the requirement for fire pump sources to be independent and reliable, and it would introduce unnecessary risks of accidental shutdown.
Takeaway: Fire pump overcurrent protection is specifically designed to carry locked-rotor current indefinitely to ensure the pump operates until failure during an emergency.
-
Question 4 of 10
4. Question
How should NEC – Article 404 (Switches) be implemented in practice when an inspector is evaluating a surface-mounted AC disconnect switch installed on the exterior of a building for a photovoltaic system in a wet location?
Correct
Correct: According to NEC 404.4(A), switches or circuit breakers installed in wet locations must be in a weatherproof enclosure. Furthermore, for surface-mounted enclosures in damp or wet locations, there must be at least 1/4 inch (6 mm) of air space between the enclosure and the wall or other supporting surface to prevent the accumulation of moisture, unless the enclosure is specifically designed and identified for direct mounting.
Incorrect: The requirement for the maximum height of the operating handle is 6 feet 7 inches (2.0 meters) per NEC 404.8(A), not 5 feet. NEC 404.2(B) generally prohibits the switching of a grounded conductor unless the switch simultaneously disconnects all conductors of the circuit. Bonding of metal faceplates for snap switches is required by NEC 404.9(B) regardless of whether the voltage is above or below 150 volts to ground to ensure user safety from electric shock.
Takeaway: Switches in wet locations require weatherproof enclosures and a 1/4-inch air gap from the mounting surface to prevent moisture-related degradation and ensure long-term equipment integrity.
Incorrect
Correct: According to NEC 404.4(A), switches or circuit breakers installed in wet locations must be in a weatherproof enclosure. Furthermore, for surface-mounted enclosures in damp or wet locations, there must be at least 1/4 inch (6 mm) of air space between the enclosure and the wall or other supporting surface to prevent the accumulation of moisture, unless the enclosure is specifically designed and identified for direct mounting.
Incorrect: The requirement for the maximum height of the operating handle is 6 feet 7 inches (2.0 meters) per NEC 404.8(A), not 5 feet. NEC 404.2(B) generally prohibits the switching of a grounded conductor unless the switch simultaneously disconnects all conductors of the circuit. Bonding of metal faceplates for snap switches is required by NEC 404.9(B) regardless of whether the voltage is above or below 150 volts to ground to ensure user safety from electric shock.
Takeaway: Switches in wet locations require weatherproof enclosures and a 1/4-inch air gap from the mounting surface to prevent moisture-related degradation and ensure long-term equipment integrity.
-
Question 5 of 10
5. Question
A new business initiative at a credit union requires guidance on NEC – Article 604 (Manufactured Wiring Systems) as part of outsourcing. The proposal raises questions about the compliance of modular power distribution units being installed in the operations center. As the lead inspector reviewing the electrical contractor’s submittals for the 120V branch circuits, you must verify that the manufactured wiring system meets specific NEC construction standards. When evaluating the cable assemblies for use in these accessible ceiling spaces, which requirement must be satisfied according to Article 604?
Correct
Correct: According to NEC 604.10(A)(1), manufactured wiring systems must use Type AC or Type MC cable containing copper insulated conductors not smaller than 12 AWG. Additionally, the code specifically requires an insulated copper equipment grounding conductor not smaller than 12 AWG to be part of the assembly.
Incorrect: Option B is incorrect because 12 AWG is the minimum size for general branch circuits in these systems; 14 AWG is only permitted for specific tap connections or signaling circuits. Option C is incorrect because Article 604 requires a dedicated insulated copper equipment grounding conductor rather than relying solely on the cable armor. Option D is incorrect because NEC 604.10 explicitly states that manufactured wiring systems are permitted in accessible locations, such as above suspended ceilings, to facilitate maintenance and reconfiguration.
Takeaway: Manufactured wiring systems must utilize at least 12 AWG copper conductors and include a dedicated insulated copper equipment grounding conductor within the cable assembly.
Incorrect
Correct: According to NEC 604.10(A)(1), manufactured wiring systems must use Type AC or Type MC cable containing copper insulated conductors not smaller than 12 AWG. Additionally, the code specifically requires an insulated copper equipment grounding conductor not smaller than 12 AWG to be part of the assembly.
Incorrect: Option B is incorrect because 12 AWG is the minimum size for general branch circuits in these systems; 14 AWG is only permitted for specific tap connections or signaling circuits. Option C is incorrect because Article 604 requires a dedicated insulated copper equipment grounding conductor rather than relying solely on the cable armor. Option D is incorrect because NEC 604.10 explicitly states that manufactured wiring systems are permitted in accessible locations, such as above suspended ceilings, to facilitate maintenance and reconfiguration.
Takeaway: Manufactured wiring systems must utilize at least 12 AWG copper conductors and include a dedicated insulated copper equipment grounding conductor within the cable assembly.
-
Question 6 of 10
6. Question
An internal review at a listed company examining NEC – Article 760 (Fire Alarm Systems) as part of internal audit remediation has uncovered that during the inspection of a 500 kW rooftop PV array, several Power-Limited Fire Alarm (PLFA) conductors were found sharing a common raceway with PV output circuits. The audit report, dated July 2023, indicates that no physical barriers were present between the two types of conductors. To ensure compliance with the National Electrical Code, what is the primary requirement for the installation of these PLFA circuits when they occupy the same enclosure as power circuits?
Correct
Correct: According to NEC 760.136, Power-Limited Fire Alarm (PLFA) conductors are generally prohibited from being placed in the same enclosure, raceway, or cable tray as power, lighting, or Class 1 circuits. One of the primary exceptions to this rule is when the different circuits are separated by a permanent, solid, and fixed barrier that is compatible with the enclosure, ensuring that the low-voltage fire alarm signals are not compromised by the higher-voltage power circuits.
Incorrect: Identifying conductors with a red jacket or using specific cable ties does not satisfy the physical separation requirements mandated by the NEC for fire alarm circuits sharing space with power circuits. Derating is a calculation used for current-carrying capacity in power conductors but does not address the safety and interference concerns of mixing PLFA and power circuits. The physical location of a sub-panel does not remediate the code violation of improper conductor separation within a shared raceway or enclosure.
Takeaway: NEC Article 760 requires strict physical separation, typically via a fixed barrier, between power-limited fire alarm circuits and power or Class 1 circuits to maintain system integrity and safety.
Incorrect
Correct: According to NEC 760.136, Power-Limited Fire Alarm (PLFA) conductors are generally prohibited from being placed in the same enclosure, raceway, or cable tray as power, lighting, or Class 1 circuits. One of the primary exceptions to this rule is when the different circuits are separated by a permanent, solid, and fixed barrier that is compatible with the enclosure, ensuring that the low-voltage fire alarm signals are not compromised by the higher-voltage power circuits.
Incorrect: Identifying conductors with a red jacket or using specific cable ties does not satisfy the physical separation requirements mandated by the NEC for fire alarm circuits sharing space with power circuits. Derating is a calculation used for current-carrying capacity in power conductors but does not address the safety and interference concerns of mixing PLFA and power circuits. The physical location of a sub-panel does not remediate the code violation of improper conductor separation within a shared raceway or enclosure.
Takeaway: NEC Article 760 requires strict physical separation, typically via a fixed barrier, between power-limited fire alarm circuits and power or Class 1 circuits to maintain system integrity and safety.
-
Question 7 of 10
7. Question
You are the information security manager at an insurer. While working on NEC – Article 725 (Class 1, Class 2, and Class 3 Remote-Control, Signaling, and Power-Limited Circuits) during transaction monitoring, you receive an incident report. During a physical inspection of a newly commissioned 500 kW solar array, you observe that the Class 2 remote-monitoring conductors for the weather station and inverter sensors are installed in the same 1.5-inch EMT conduit as the 480V AC power feeders. The site supervisor argues that because the Class 2 conductors are rated for 600V, they meet the requirements for shared raceways. How should you address this finding in your inspection report?
Correct
Correct: According to NEC 725.136(A), Class 2 and Class 3 circuit conductors cannot be placed in any enclosure, raceway, or cable with conductors of electric light, power, or Class 1 circuits. The fact that the Class 2 wire has 600V insulation does not permit it to be mixed with power conductors in the same raceway, as the separation is required to prevent high-voltage contact with low-voltage systems in the event of insulation failure or improper handling.
Incorrect: The general rules in Article 300 regarding conductors of different systems are superseded by the specific requirements in Article 725 for Class 2 and 3 circuits. There is no NEC requirement that Class 2 circuits must be in PVC; EMT is a valid wiring method, but not when shared with power. Shielding and grounding do not waive the physical separation requirements mandated by the NEC for these circuit classes.
Takeaway: NEC Article 725 requires strict physical separation between Class 2/3 low-voltage circuits and power/Class 1 circuits to ensure system safety and integrity.
Incorrect
Correct: According to NEC 725.136(A), Class 2 and Class 3 circuit conductors cannot be placed in any enclosure, raceway, or cable with conductors of electric light, power, or Class 1 circuits. The fact that the Class 2 wire has 600V insulation does not permit it to be mixed with power conductors in the same raceway, as the separation is required to prevent high-voltage contact with low-voltage systems in the event of insulation failure or improper handling.
Incorrect: The general rules in Article 300 regarding conductors of different systems are superseded by the specific requirements in Article 725 for Class 2 and 3 circuits. There is no NEC requirement that Class 2 circuits must be in PVC; EMT is a valid wiring method, but not when shared with power. Shielding and grounding do not waive the physical separation requirements mandated by the NEC for these circuit classes.
Takeaway: NEC Article 725 requires strict physical separation between Class 2/3 low-voltage circuits and power/Class 1 circuits to ensure system safety and integrity.
-
Question 8 of 10
8. Question
Excerpt from a customer complaint: In work related to Identifying potential electrical hazards and their associated risks as part of business continuity at an audit firm, it was noted that during a Q3 facility walkthrough of the primary data center, several 480V switchgear sections lacked visible arc flash hazard labels. The facility manager noted that the system underwent a significant expansion 18 months ago, but the original hazard analysis was not updated to reflect the new configuration. Technicians are currently scheduled to perform routine voltage measurements and thermal imaging on this energized equipment next week. Given the lack of current hazard data and the potential for high incident energy, what is the most critical risk identified and the necessary professional response?
Correct
Correct: According to NFPA 70E and OSHA standards, electrical equipment such as switchgear that is likely to require examination, adjustment, or maintenance while energized must be field-marked with arc flash hazard labels. The absence of these labels means that qualified personnel cannot determine the incident energy level or the required Personal Protective Equipment (PPE) category. Consequently, the most appropriate professional action is to restrict all energized work on the affected equipment until a formal arc flash hazard analysis is conducted and the equipment is properly labeled, ensuring that any future interactions are guided by accurate risk data.
Incorrect: Focusing on thermal monitoring through infrared windows is a valid maintenance strategy for identifying loose connections but does not address the immediate safety hazard of unknown incident energy levels for personnel. Verifying grounding and bonding is critical for system stability and fault clearing, yet it does not mitigate the specific risks associated with an arc flash or provide the necessary hazard communication for workers. Adjusting circuit breaker trip settings to prevent nuisance tripping addresses operational reliability and coordination but fails to provide the safety information required to protect technicians from thermal or pressure hazards during a fault event.
Takeaway: The absence of arc flash hazard labels constitutes a critical safety failure that prevents the determination of necessary PPE, requiring a suspension of energized work until a formal hazard assessment is completed.
Incorrect
Correct: According to NFPA 70E and OSHA standards, electrical equipment such as switchgear that is likely to require examination, adjustment, or maintenance while energized must be field-marked with arc flash hazard labels. The absence of these labels means that qualified personnel cannot determine the incident energy level or the required Personal Protective Equipment (PPE) category. Consequently, the most appropriate professional action is to restrict all energized work on the affected equipment until a formal arc flash hazard analysis is conducted and the equipment is properly labeled, ensuring that any future interactions are guided by accurate risk data.
Incorrect: Focusing on thermal monitoring through infrared windows is a valid maintenance strategy for identifying loose connections but does not address the immediate safety hazard of unknown incident energy levels for personnel. Verifying grounding and bonding is critical for system stability and fault clearing, yet it does not mitigate the specific risks associated with an arc flash or provide the necessary hazard communication for workers. Adjusting circuit breaker trip settings to prevent nuisance tripping addresses operational reliability and coordination but fails to provide the safety information required to protect technicians from thermal or pressure hazards during a fault event.
Takeaway: The absence of arc flash hazard labels constitutes a critical safety failure that prevents the determination of necessary PPE, requiring a suspension of energized work until a formal hazard assessment is completed.
-
Question 9 of 10
9. Question
The board of directors at an investment firm has asked for a recommendation regarding Local Authority Having Jurisdiction (AHJ) Requirements as part of whistleblowing. The background paper states that several solar assets within a 50-megawatt portfolio were permitted and installed during a transitional period when the local municipality was moving from the 2017 NEC to the 2020 NEC. A whistleblower alleges that the systems do not meet the rapid shutdown requirements mandated by the newer code cycle, even though the permits were finalized 90 days after the official adoption date of the 2020 NEC. When performing a system inspection to verify these claims, what is the primary regulatory obligation regarding code compliance?
Correct
Correct: The Authority Having Jurisdiction (AHJ) is the legal entity responsible for enforcing the building and electrical codes within a specific area. Compliance is determined by the specific version of the NEC and any local amendments that have been officially adopted by that jurisdiction at the time the permit is issued. Even if a newer version of the NEC exists, it is not enforceable until the local government formally adopts it.
Incorrect: The most recent NFPA standards are not automatically enforceable until adopted by the local or state government. Manufacturer instructions are critical under NEC 110.3(B) but do not supersede the adopted code; they must be followed in addition to the code. Contract dates between private parties have no bearing on regulatory compliance or the legal requirements set forth by the AHJ.
Takeaway: PV system inspectors must evaluate installations based on the specific code editions and local amendments officially adopted by the AHJ at the time of permitting.
Incorrect
Correct: The Authority Having Jurisdiction (AHJ) is the legal entity responsible for enforcing the building and electrical codes within a specific area. Compliance is determined by the specific version of the NEC and any local amendments that have been officially adopted by that jurisdiction at the time the permit is issued. Even if a newer version of the NEC exists, it is not enforceable until the local government formally adopts it.
Incorrect: The most recent NFPA standards are not automatically enforceable until adopted by the local or state government. Manufacturer instructions are critical under NEC 110.3(B) but do not supersede the adopted code; they must be followed in addition to the code. Contract dates between private parties have no bearing on regulatory compliance or the legal requirements set forth by the AHJ.
Takeaway: PV system inspectors must evaluate installations based on the specific code editions and local amendments officially adopted by the AHJ at the time of permitting.
-
Question 10 of 10
10. Question
After identifying an issue related to Application for Permits, what is the best next step? An inspector reviewing a residential PV permit application discovers that the site plan fails to account for a newly installed plumbing vent that now encroaches on the required fire department ventilation pathways as specified in the local building code.
Correct
Correct: The permitting process is designed to ensure that the proposed installation complies with all safety codes, including fire setbacks, before work begins. When a discrepancy is found between the site conditions and the permit application, the applicant must provide updated documentation to the AHJ. This ensures the plan review process accounts for the actual physical constraints of the roof and maintains the integrity of the safety standards mandated by the building and fire codes.
Incorrect: Allowing the installation to proceed with only a field note is insufficient because the AHJ must verify that the revised layout still meets all code requirements before construction. Reducing the number of modules without an amended plan bypasses the formal review process and may lead to further electrical or structural inconsistencies. Signed affidavits from homeowners cannot override safety codes or legal permitting requirements established by the jurisdiction.
Takeaway: Any significant deviation from the site conditions in a permit application requires a formal plan revision and AHJ approval to ensure continued compliance with fire and building codes.
Incorrect
Correct: The permitting process is designed to ensure that the proposed installation complies with all safety codes, including fire setbacks, before work begins. When a discrepancy is found between the site conditions and the permit application, the applicant must provide updated documentation to the AHJ. This ensures the plan review process accounts for the actual physical constraints of the roof and maintains the integrity of the safety standards mandated by the building and fire codes.
Incorrect: Allowing the installation to proceed with only a field note is insufficient because the AHJ must verify that the revised layout still meets all code requirements before construction. Reducing the number of modules without an amended plan bypasses the formal review process and may lead to further electrical or structural inconsistencies. Signed affidavits from homeowners cannot override safety codes or legal permitting requirements established by the jurisdiction.
Takeaway: Any significant deviation from the site conditions in a permit application requires a formal plan revision and AHJ approval to ensure continued compliance with fire and building codes.